BUSINESS PROCESS OUTSOURCE OFFICE

Scope of Work     :

Civil, architectural, and piping works for the construction of a recruitment office with a total floor area of 270 square meters.

Location              :

Ground Floor, Vertex One Building, San Lazaro Tourism & Business Park, Manila

Client                  :

Convergys Philippines Services Corporation

Date Completed  :

September 2009


OFFICE RECONFIGURATION

Scope of Work     :

Reconfiguration of office spaces at the 10/F and 18/F of the GBS Offices

Location              :

10th and 18th Floor Petron Mega Plaza Sen. Gil Puyat Avenue, Makati City

Client                  :

Procter & Gamble Asia Pte. Ltd.

Date Completed  :

May 2009


BUSINESS PROCESS OUTSOURCE OFFICE

Scope of Work     :

Civil, architectural, and piping works for the construction of a BPO office with a total floor area of 4,500 square meters.

Location              :

7th and 8th Floors, Vertex One Building, San Lazaro Tourism & Business Park, Manila

Client                  :

Convergys Philippines Services Corporation

Date Completed  :

April 2009


CORPORATE OFFICE

Scope of Work     :

Architectural, mechanical, electrical, and piping works for the construction of a corporate office with a total floor area of 1,400 square meters.

Location              :

24th Floor Petron Mega Plaza Sen. Gil Puyat Avenue, Makati City

Client                 :

Procter & Gamble Asia Pte. Ltd.

Date Completed  :

January 2009


OFFICE PROJECT

Scope of Work     :

Architectural, electrical, and piping works for 150 sqm central storage space.

Location              :

9/F RCBC Plaza, Sen. Gil Puyat Avenue, Makati City

Client                 :

The Canadian Embassy Manila

Date Completed  :

September 2008


CORPORATE OFFICE

Scope of Work     :

Architectural an electrical works for the renovation of a corporate office

Location              :

8/F Floor Kings Court I 2129 Pasong Tamo, Makati City

Client                  :

Davis Langdon & Seah Philippines Inc.

Date Completed  :

July 2008


CORPORATE OFFICE

Scope of Work     :

Architectural and electrical works for the partial renovation of a corporate office.

Location              :

17/F Standard Chartered Bank 6788 Ayala Avenue, Makati City

Client                  :

NCR Corporation (Philippines)

Date Completed  :

May 2008


CORPORATE OFFICE

Scope of Work     :

Architectural, mechanical, electrical, and piping works for the construction of a corporate office with a total floor area of 1,400 square meters.

Location              :

11th Floor Petron Mega Plaza Sen. Gil Puyat Avenue, Makati City

Client                  :

Procter & Gamble Asia Pte. Ltd.

Date Completed  :

March 2008


CORPORATE OFFICE

Scope of Work     :

Architectural, mechanical, electrical, and piping works for the construction of a corporate office with a total floor area of 1,700 sqm.

Location              :

2/F and 3/F 111 Paseo de Roxas, Legaspi Village Makati City

Client                  :

GHD Pty. Ltd.

Date Completed  :

February 2008


CORPORATE OFFICE

Scope of Work     :

Electrical and fire detection and alarm system works for the construction of a corporate office with a total floor area of 800 square meters.

Location              :

4/F RCBC Plaza, Sen. Gil Puyat Avenue, Makati City

Client                  :

IP-Converge Data Center, Inc.

Date Completed  :

February 2008


CORPORATE OFFICE

Scope of Work     :

Architectural, electrical, and piping works for the construction of a corporate office with a total floor area of 450 square meters.

Location              :

18/F Robinsons Equitable Tower ADB Avenue, Ortigas Center, Pasig City

Client                  :

Mundipharma Distribution GmbH

Date Completed  :

November 2007


CORPORATE OFFICE

Scope of Work     :

Architectural and electrical works for the partial refurbishing of a corporate office.

Location              :

10th, 18th, 19th, 20th, 22nd, and 23rd Floors, Petron Mega Plaza, Sen. Gil Puyat Avenue, Makati City

Client                  :

Procter & Gamble Asia Pte. Ltd.

Date Completed  :

October 2007


CORPORATE OFFICE

Scope of Work     :

Architectural works for the partial refurbishing of a corporate office.

Location              :

19/F Tower 2, The Enterprise Center 6766 Ayala Avenue, Makati City

Client                  :

Credit Suisse

Date Completed  :

October 2007


CORPORATE OFFICE

Scope of Work     :

Architectural, mechanical, electrical, and piping works for the complete renovation of the 21st floor , partial renovation of the 20th floor and partial reinstatement of the 19th floor. Total project area was 2,500 square meters.

Location              :

19th, 20th, 21st Floor 6750 Ayala Office Tower Ayala Avenue, Makati City

Client                  :

Procter & Gamble Asia Pte. Ltd.

Date Completed  :

September 2007


BUSINESS PROCESS OUTSOURCE OFFICE

Scope of Work     :

Architectural, mechanical, electrical, and piping works for the construction of a corporate office with a total floor area of 1,000 sqm.

Location              :

18th Floor, San Miguel Properties Centre, St. Francis Avenue, Mandaluyong City

Client                  :

Hewlett-Packard Philippines Corporation

Date Completed  :

July 2007


CORPORATE OFFICE

Scope of Work     :

Architectural, mechanical, electrical, and piping works for the reinstatement of a corporate office with a total floor area of 500 sqm.

Location              :

15th Floor 6750 Ayala Office Tower Ayala Avenue, Makati City

Client                  :

Procter & Gamble Asia Pte. Ltd.

Date Completed  :

April 2007


BUSINESS PROCESS OUTSOURCE OFFICES

Scope of Work     :

Architectural, mechanical, electrical and piping works for a corporate office with a total floor area of 4,500 sqm.

Location              :

10th, 18th, 19th, 20th, 22nd, & 23rd Floors Petron Mega Plaza, Sen. Gil Puyat Avenue, Makati City

Client                  :

Procter & Gamble Asia Pte. Ltd.

Date Completed  :

May 2006


CORPORATE OFFICE

Scope of Work     :

Architectural, mechanical, electrical and piping works for a corporate office with a total floor area of 1,200 sqm.

Location              :

20th Floor 6750 Ayala Office Tower Ayala Avenue, Makati City

Client                  :

Procter & Gamble Asia Pte. Ltd.

Date Completed  :

March 2006


AUTOMOBILE SHOWROOM

Scope of Work     :

Architectural works for a 600 square meter automobile showroom

Location              :

Bicutan, Parañaque

Client                  :

Toyota Motor Philippines, Inc.

Date Completed  :

July 2005


CORPORATE OFFICE

Scope of Work     :

Architectural, mechanical, electrical and piping works for a corporate office with a total floor area of 220 square meters

Location              :

2/F The Taipan Place, Emerald Avenue, Pasig City

Client                  :

Mundi Pharma Philippines, Inc.

Date Completed  :

March 2005


CORPORATE OFFICE

Scope of Work     :

Architectural, electrical, mechanical and piping works for a corporate office with a floor area of 1,000 square meters

Location              :

Wynsum Corporate Plaza Emerald Avenue, Ortigas Center

Client                  :

Eli Lilly Philippines, Inc.

Date Completed  :

October 2004


BUSINESS PROCESS OUTSOURCE OFFICES

Scope of Work     :

Architectural, MVAC, electrical, and piping works for a corporate office reconfiguration with a total floor area of 350 square meters.

Location              :

17/F & 18/F 6750 Ayala Avenue, Makati City

Client                  :

Procter & Gamble Philippines, Inc.

Date Completed  :

December 2003


CORPORATE AND BUSINESS PROCESS OUTSOURCE OFFICES

Scope of Work     :

Architectural, MVAC, electrical, fire protection, and plumbing works for the headquarters of a multi-national consumer goods company, with a total floor area of 6,000 square meters.

Location              :

15/F, 16/F, 18/F,19/F, and 21/F 6750 Ayala Avenue, Makati City

Client                  :

Procter & Gamble Philippines, Inc.

Date Completed  :

April 2003


CORPORATE OFFICES & LABORATORIES

Scope of Work     :

Architectural, mechanical, and electrical works for the construction of an office and laboratory with a floor area of 600 square meters.

Location              :

37/F Robinsons-Equitable Bank Tower Ortigas Center, Pasig City

Client                  :

Quest International Cebu, Inc.

Date Completed  :

September 2002


OFFICE RECONFIGURATION

Scope of Work     :

Architectural, MVAC, and electrical works for the expansion of the Treasury Room, a floor area of 110 square meters.

Location              :

P&G GBS, 18/F Petron Mega Plaza G. Puyat Avenue, Makati City

Client                  :

Procter & Gamble Philippines, Inc.

Date Completed  :

April 2001


CORPORATE OFFICE

Scope of Work     :

Architectural and electrical works for the construction of an office with a floor area of 300 square meters.

Location              :

16/F Orient Square, Emerald Avenue Ortigas Center, Pasig City

Client                  :

ExxonMobil Petroleum & Chemical Holdings, Inc.

Date Completed  :

March 2001


BUSINESS PROCESS OUTSOURCE OFFICES

Scope of Work     :

Architectural, MVAC, electrical, and plumbing works for a corporate office with a total floor area of 3,550 square meters.

Location              :

18/F, 19/F, and 20/F Petron Mega Plaza Sen. Gil Puyat Avenue, Makati City

Client                  :

Procter & Gamble Philippines, Inc.

Date Completed  :

July 2000


VENEERED PANEL INSTALLATION

Scope of Work     :

Installation of wood panelling for the Quad IV mixed-use development project.

Location              :

Oakwood Suites, Ayala Center, Makati City

Client                  :

Ayala Hotels, Inc.

Date Completed  :

October 1999


CORPORATE OFFICE

Scope of Work     :

Architectural and plumbing works for a 350 square meter office of former Philippine president, Fidel V. Ramos

Location              :

21/F Urban Bank Plaza Urban Avenue, Makati City

Client                  :

Ramos Peace and Development Foundation

Date Completed  :

August 1999


LAW OFFICE

Scope of Work     :

Architectural, electrical, and plumbing works for a 501 square meter law office.

Location              :

21/F Robinsons-PCIBank Tower ADB Avenue, Ortigas Center, Pasig City

Client                  :

Quiason Makalintal Barot Torres and Ibarra Law Firm

Date Completed  :

July 1999


BANK REGIONAL OFFICE

Scope of Work     :

Architectural and plumbing works for a 850 square meter bank regional office.

Location              :

G/F and 2/F, Calereice Corporate Condominium, Madrigal Business Park Alabang, Muntinlupa

Client                  :

Urban Bank

Date Completed  :

July 1999


BUSINESS CENTER / EXECUTIVE LOUNGE

Scope of Work     :

Architectural, structural, electrical, and plumbing works for a 1,200 square meter business center and a 650 square meter penthouse lounge.

Location              :

24/F & penthouse lounge, Urban Bank Plaza Urban Avenue, Makati City

Client                  :

Urban Bank

Date Completed  :

April 1999


CORPORATE EXECUTIVE OFFICES

Scope of Work     :

Architectural, electrical, and plumbing works for a 1,200 square meter office.

Location              :

37/F Urban Bank Plaza Urban Avenue, Makati City

Client                  :

Urban Bank

Date Completed  :

February 1999


BANK REGIONAL OFFICE

Scope of Work     :

Architectural, electrical, and plumbing works for a 900 square meter bank regional office.

Location              :

G/F and 14/F, Ayala Life-FGU Center Cebu Business Park, Cebu City

Client                  :

Urban Bank

Date Completed  :

February 1999